[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151468":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151468,803,2,"多选题","根据根据《水利水电建设工程验收规程》SL223-2008，合同工程完工验收后，在项目法人颁发合同工程完工证书前，施工单位完成的工作包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程移交运行管理单位",false,{"key":16,"text":17,"correct":14},"B","验收遗留问题处理",{"key":19,"text":20,"correct":21},"C","提交工程质量保修书",true,{"key":23,"text":24,"correct":21},"D","提交竣工资料",{"key":26,"text":27,"correct":21},"E","施工场地清理","CDE","在施工单位递交了工程质量保修书、完成施工场地清理以及提交有关竣工资料后，项目法人应在30 个工作日内向施工单位颁发经单位法定代表人签字的合同工程完工证书。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]