[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151447":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151447,803,2,"多选题","根据《水利工程设计变更管理暂行办法》（水规计[2012]93 号），下列施工组织设计变更中，属于重大设计变更的是（ ）的变化。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","主要料场场地",true,{"key":16,"text":17,"correct":14},"B","枢纽工程施工导流方式",{"key":19,"text":20,"correct":14},"C","导流建筑物方案",{"key":22,"text":23,"correct":14},"D","主要建筑物工程总进度",{"key":25,"text":26,"correct":27},"E","地下洞室支护形式",false,"ABCD","E：一般设计变更。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]