[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151421":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151421,803,2,"多选题","关于水利工程施工期间外部变形监测的说法，正确的是（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","监测控制点的精度应不低于四等网的标准",true,{"key":16,"text":17,"correct":18},"B","基点必须建立在变形区以内稳固的基岩上",false,{"key":20,"text":21,"correct":14},"C","测点应与变形件牢固结合",{"key":23,"text":24,"correct":18},"D","滑坡测点宜设在滑动量小的部位",{"key":26,"text":27,"correct":14},"E","山体裂缝观测点应埋设在裂缝两侧","ACE","B：基点必须建立在变形区以外稳固的基岩上。D：滑坡测点宜设在滑动量大的部位。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]