[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151413":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151413,803,2,"多选题","关于施工现场临时10kv 变压器安装的说法中，正确的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","变压器装于地面时，应有0.5m 的高台",true,{"key":16,"text":17,"correct":14},"B","装于地面的变压器周围应装设栅栏",{"key":19,"text":20,"correct":21},"C","杆上变压器安装的高度应不低于1.0m",false,{"key":23,"text":24,"correct":14},"D","杆上变压器应挂有“止步、高压危险”的警示标志",{"key":26,"text":27,"correct":14},"E","变压器的引线应采用绝缘导线","ABDE","现场临时变压器安装施工用的10kv 及以下变压器装于地面时, 应有0.5m 的高台, 高台的周围应装设栅栏, 其高度不低于1.7m。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]