[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151401":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151401,803,2,"多选题","堤防压实作业前碾压试验需确定的碾压参数包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","碾压遍数",true,{"key":16,"text":17,"correct":14},"B","铺土厚度",{"key":19,"text":20,"correct":21},"C","含水率",false,{"key":23,"text":24,"correct":21},"D","振动频率",{"key":26,"text":27,"correct":21},"E","行走速率","AB","堤防压实碾压试验参数包括机具、碾压遍数、铺土厚度、含水量、土块限制直径。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]