[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151365":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151365,803,2,"多选题","（2014年）根据《水电水利工程施工监理规范》（DL\u002FT5111—2000），水力发电工程的工程变更分为（）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","常规设计变更",true,{"key":16,"text":17,"correct":14},"B","一般工程变更",{"key":19,"text":20,"correct":14},"C","较大工程变更",{"key":22,"text":23,"correct":14},"D","重大工程变更",{"key":25,"text":26,"correct":27},"E","特别重大工程变更",false,"ABCD","工程变更依据其性质与对工程项目的影响程度，分为重大工程变更、较大工程变更、一般工程变更、常规设计变更四类。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]