[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151362":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151362,803,2,"多选题","（2015年）根据《水电工程验收管理办法》（国能新能〔2011〕263号），下列验收由省级人民政府能源主管部门负责的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程蓄水验收",true,{"key":16,"text":17,"correct":18},"B","工程截流验收",false,{"key":20,"text":21,"correct":18},"C","水轮发电机组启动验收",{"key":23,"text":24,"correct":14},"D","枢纽工程专项验收",{"key":26,"text":27,"correct":14},"E","竣工验收","ADE","工程蓄水验收、枢纽工程专项验收和工程竣工验收由省级人民政府能源主管部门负责，并委托有业绩、能力单位作为技术主持单位组织验收委员会进行。工程截流验收由项目法人会同省级发展改革委、能源主管部门共同组织验收委员会；水轮发电机组启动验收由由项目法人会同电网经营管理单位共同组织验收委员会进行。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]