[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151347":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151347,803,2,"多选题","（2018年真题）根据《水利基本建设项目竣工决算审计规程》（SL557-2012）,审计终结阶段要进行的工作包括（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","下达审计结论",false,{"key":16,"text":17,"correct":14},"B","征求意见",{"key":19,"text":20,"correct":14},"C","出具审计报告",{"key":22,"text":23,"correct":24},"D","整改落实",true,{"key":26,"text":27,"correct":24},"E","后续审计","DE","本题考查的是水利工程建设稽察、决算与审计的内容。竣工决算审计的程序应包括以下四个阶段：（1）审计准备阶段。包括审计立项、编制审计实施方案、送达审计通知书等环节。（2）审计实施阶段。包括收集审计证据、编制审计工作底稿、征求意见等环节。（3）审计报告阶段。包括出具审计报告、审计报告处理、下达审计结论等环节。（4）审计终结阶段。包括整改落实和后续审计等环节。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]