[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151345":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151345,803,2,"多选题","（2019年真题）水利PPP项目实施程序主要包括()。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","项目储备",true,{"key":16,"text":17,"correct":14},"B","项目论证",{"key":19,"text":20,"correct":14},"C","社会资本方选择",{"key":22,"text":23,"correct":14},"D","项目执行",{"key":25,"text":26,"correct":27},"E","设备采购",false,"ABCD","P152-164 本题考查的是政府和社会资本合作(PPP模式)。水利PPP项目实施程序主要包括项目储备、项目论证、社会资本方选择、项目执行等。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]