[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151343":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151343,803,2,"多选题","（2016年）水利工程建设程序中，立项过程包括（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","项目建议书",true,{"key":16,"text":17,"correct":14},"B","可行性研究报告",{"key":19,"text":20,"correct":21},"C","初步设计",false,{"key":23,"text":24,"correct":21},"D","施工准备",{"key":26,"text":27,"correct":21},"E","施工招标","AB","立项过程：项目建议书、可行性研究报告。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]