[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151341":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151341,803,2,"多选题","（2010年）水利工程建设项目审计按建设过程分为（）审计。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","前期工作",false,{"key":16,"text":17,"correct":18},"B","开工",true,{"key":20,"text":21,"correct":18},"C","建设期间",{"key":23,"text":24,"correct":18},"D","竣工决算",{"key":26,"text":27,"correct":14},"E","竣工后","BCD","1.水利工程基本建设项目审计按建设管理过程分为开工审计、建设期间审计和竣工决算审计。 2.其中开工审计、建设期间审计，水利审计部门可根据项目性质、规模和建设管理的需要进行； 3.竣工决算审计在项目正式竣工验收之前必须进行。 4.竣工决算审计是指水利基本建设项目竣工验收前，水利审计部门对其竣工决算的真实性、合法性和效益性进行的审计监督和评价。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]