[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151338":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151338,803,2,"多选题","（2012年）根据《水利工程建设项目管理规定》（水建[1995]128号），在水利工程建设程序中，属于前期工作的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","项目建设书",true,{"key":16,"text":17,"correct":14},"B","可行性研究报告",{"key":19,"text":20,"correct":14},"C","初步设计",{"key":22,"text":23,"correct":24},"D","招标设计",false,{"key":26,"text":27,"correct":24},"E","生产准备","ABC","项目建议书、可行性研究报告、初步设计称为前期工作。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]