[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151324":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151324,803,2,"多选题","（2011年）关于新筑堤防作业的说法，正确的有（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","作业面应水平分层，不得顺坡铺填",true,{"key":16,"text":17,"correct":14},"B","机械施工时，分段作业面长度不应小于100m",{"key":19,"text":20,"correct":14},"C","分段作业面上、下层不得在同一位置分段",{"key":22,"text":23,"correct":24},"D","碾压机具行走方向，不得平行于堤轴线",false,{"key":26,"text":27,"correct":14},"E","土料铺填与压实工序应连续进行","ABCE","1.碾压行走方向，应平行于堤轴线。 2.分段、分片碾压，相邻作业面的搭接碾压宽度，平行堤轴线方向不应小于0.5m；垂直堤轴线方向不应小于3m。 3.土料含水率应控制在最优含水率±3％范围内。 4.砂砾料压实时，洒水量宜为填筑方量的20％～40％。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]