[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151305":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151305,803,2,"多选题","（2009年）反铲挖掘机每一作业循环包括（ )等过程。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","挖掘",true,{"key":16,"text":17,"correct":18},"B","运土",false,{"key":20,"text":21,"correct":14},"C","回转",{"key":23,"text":24,"correct":14},"D","卸料",{"key":26,"text":27,"correct":14},"E","返回","ACDE","每一作业循环包括挖掘、回转、卸料和返回等四个过程",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]