[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151297":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151297,803,2,"多选题","（2016年）水利工程施工中，基坑经常性排水量的组成包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","围堰渗流量",true,{"key":16,"text":17,"correct":14},"B","覆盖层含水量",{"key":19,"text":20,"correct":14},"C","施工弃水量",{"key":22,"text":23,"correct":24},"D","坑初期积水量",false,{"key":26,"text":27,"correct":14},"E","排水时段降水量","ABCE","经常性排水应分别计算围堰和地基在设计水头的渗流量、覆盖层中的含水量、排水时降水量及施工弃水量。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]