[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151295":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151295,803,2,"多选题","（2010年）土坝截流施工中，改善龙口水力条件的措施包括（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","定向爆破",false,{"key":16,"text":17,"correct":18},"B","双戗截流",true,{"key":20,"text":21,"correct":18},"C","三戗截流",{"key":23,"text":24,"correct":18},"D","宽戗截流",{"key":26,"text":27,"correct":18},"E","平抛垫底","BCDE","改善龙口水力条件：双戗截流、三戗截流、宽戗截流、平抛垫底",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]