[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151276":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1151276,803,1,"单选题","根据《水电水利工程爆破施工技术规范》DL\u002FT5135-2013，地下洞室爆破时，爆破人员应在爆破后（ ）min，并经检查确认洞室内空气合格后，进人工作面进行检查。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","5",false,{"key":16,"text":17,"correct":14},"B","10",{"key":19,"text":20,"correct":21},"C","15",true,{"key":23,"text":24,"correct":14},"D","30","2020版教材P398 \u002F 2019版教材P397 地下洞室爆破应在爆破后15min，并经检查确认洞室内空气合格后，方可准许人员进人工作面。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]