[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151275":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1151275,803,1,"单选题","根据《水电水利工程爆破施工技术规范》DL\u002FT5135-2013，明挖爆破时，爆破人员应在爆破后（ ）min进人工作面进行检查。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5",true,{"key":16,"text":17,"correct":18},"B","10",false,{"key":20,"text":21,"correct":18},"C","15",{"key":23,"text":24,"correct":18},"D","30","2020版教材P398 \u002F 2019版教材P397 明挖爆破时，应在爆破后5min进入工作面；当不能确认有无盲炮时，应在爆破后15min进入工作面。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]