[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151258":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1151258,803,1,"单选题","大中型水利水电工程建设项目用地，应当依法申请并办理审批手续，实行（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","一次报批、一次征收，一次支付征地补偿费",false,{"key":16,"text":17,"correct":18},"B","一次报批、分期征收，按期支付征地补偿费",true,{"key":20,"text":21,"correct":14},"C","分期报批、分期征收，分期支付征地补偿费",{"key":23,"text":24,"correct":14},"D","分期报批、分期征收，按期支付征地补偿费","2020版教材P382 \u002F 2019版教材P381 《条例》第二十一条规定：“大中型水利水电工程建设项目用地,应当依法申请并办理审批手续，实行一次报批、分期征收，按期支付征地补偿费",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]