[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151207":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1151207,803,1,"单选题","水利工程保护范围内的土地应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","与工程占地范围一起征用",false,{"key":16,"text":17,"correct":18},"B","不征用",true,{"key":20,"text":21,"correct":14},"C","由工程管理单位进行管理",{"key":23,"text":24,"correct":14},"D","临时征用","2020版教材P369 \u002F 2019版教材P368 工程和水库保护范围内的土地不征用,应根据工程管理的要求和有关法规制订保护范围的管理办法。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]