[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151201":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1151201,803,1,"单选题","不合格单元工程必须经返工或补工合格并取得（ ）认证后，方准予进入下道工序或后序单元工程开工。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目法人",false,{"key":16,"text":17,"correct":14},"B","质监机构",{"key":19,"text":20,"correct":14},"C","水行政主管部门",{"key":22,"text":23,"correct":24},"D","监理工程师",true,"2020版教材P331 \u002F 2019版教材P330 水力发电工程监理合同商务管理的内容中的工程质量检验。不合格单元工程必须经返工或补工合格并取得监理工程师认证后，方准予进人下道工序或后序单元工程开工。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]