[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151196":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1151196,803,1,"单选题","最后一笔保留金的支付时间是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","合同项目完工并终止后",false,{"key":16,"text":17,"correct":14},"B","合同项目完工并签发工程移交证书之后",{"key":19,"text":20,"correct":21},"C","工程缺陷责任期满之后",true,{"key":23,"text":24,"correct":14},"D","最终决算","2020版教材P332 \u002F 2019版教材P331 合同项目完工并签发工程移交证书之后，监理机构应协助业主及时按合同约定的保留金的一部分付给承建单位，并为此签发保留金付款证书；当工程缺陷责任期满之后，监理机构应协助业主及时将剩余部分保留金付给承建单位，并为此签发保留金付款证书。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]