[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151195":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1151195,803,1,"单选题","工程价款支付一般按（ ）进行。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","月",true,{"key":16,"text":17,"correct":18},"B","季度",false,{"key":20,"text":21,"correct":18},"C","半年",{"key":23,"text":24,"correct":18},"D","年","2020版教材P332 \u002F 2019版教材P331 水力发电工程监理合同费用控制的内容，工程施工阶段监理机构工程合同费用控制的主要任务。工程价款支付。工程价款支付属合同履行过程的中期支付，按月进行。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]