[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151194":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1151194,803,1,"单选题","工程变更指令一般由（ ）审查、批准后发出。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","业主或业主授权监理机构",true,{"key":16,"text":17,"correct":18},"B","设计单位",false,{"key":20,"text":21,"correct":18},"C","质量监督机构",{"key":23,"text":24,"correct":18},"D","承建单位","2020版教材P332 \u002F 2019版教材P331 水力发电工程监理合同商务管理的内容工程变更。工程变更指令由业主或业主授权监理机构审查、批准后发出。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]