[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151193":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1151193,803,1,"单选题","施工进度计划的编制单位是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设单位",false,{"key":16,"text":17,"correct":14},"B","设计单位",{"key":19,"text":20,"correct":14},"C","监理单位",{"key":22,"text":23,"correct":24},"D","承建单位",true,"2020版教材P332 \u002F 2019版教材P331 水力发电工程监理进度控制的内容中施工进度计划的编制与审批。施工进度计划，施工进度计划是批准工程开工的重要依据。承建单位应在工程项目开X前，随同施工组织设计或施工措施计划,向监理机构报批施工进度计划。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]