[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151192":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1151192,803,1,"单选题","在水力发电工程中，下列关于工程变更、合同索赔的说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程变更指令由业主或业主授权监理发出",false,{"key":16,"text":17,"correct":14},"B","监理机构可以拒绝或同意合同索赔的全部或部分要求",{"key":19,"text":20,"correct":14},"C","设计单位可以提出要求或建议",{"key":22,"text":23,"correct":24},"D","索赔争议仲裁、调解过程中，合同双方应停止工程承建合同文件规定的义务和责任",true,"2020版教材P333 \u002F 2019版教材P332 水力发电工程监理合同商务管理的内容。在合同索赔事项发生后合同索赔处理过程中，或在索赔争议调解、仲裁过程中，合同双方仍应履行工程承建合同文件规定的义务与责任，不得因此而影响工程施工的照常进行。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]