[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151182":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1151182,803,1,"单选题","水利工程建设项目施工监理施工准备阶段监理工作的基本内容是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","检查开工前由发包人准备的施工条件和承包人的施工准备情况",true,{"key":16,"text":17,"correct":18},"B","复核发包人提供的测量基准点，签发进场通知、审批开工申请",false,{"key":20,"text":21,"correct":18},"C","协助发包人编制年、月的合同付款计划，审批承包人提交的资金流计划",{"key":23,"text":24,"correct":18},"D","协助发包人编制控制性总进度计划，审批承包人提交的施工进度计划","2020版教材P328 \u002F 2019版教材P327 根据有关规范和规定，水利工程建设项目施工监理施工准备阶段监理工作的基本内容是：1.检查开工前发包人应提供的施工条件是否满足开工要求。2.检查开工前承包人的施工准备情况3.监理机构应参加、主持或与发包人联合主持召开设计交底会议，由设计单位进行设计文件的技术交底。4.施工图纸的核查与签发应符合相关规定。5.参与发包人组织的工程质量评定项目划分。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]