[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151181":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1151181,803,1,"单选题","检查由发包人提供的道路、供电、供水、通信等条件的完成情况是施工监理（ ）阶段的工作内容。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工准备",true,{"key":16,"text":17,"correct":18},"B","施工计划",false,{"key":20,"text":21,"correct":18},"C","施工实施",{"key":23,"text":24,"correct":18},"D","质量控制","2020版教材P328 \u002F 2019版教材P327 根据有关规范和规定，水利工程建设项目施工监理施工准备阶段监理工作的基本内容是检查开工前发包人应提供的施工条件是否满足开工要求。1.检查开工前由发包人准备的施工条件情况：1、首批开工项目施工图纸的提供；2、测量基准点的移交；3、施工用地的提供；4、施工合同约定应由发包人负责的道路、供电、供水、通信及其他条件和资源的提供情况。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]