[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151172":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1151172,803,1,"单选题","根据《水利建筑工程预算定额》，推土机推松土时定额调整系数为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.7",false,{"key":16,"text":17,"correct":18},"B","0.8",true,{"key":20,"text":21,"correct":14},"C","0.9",{"key":23,"text":24,"correct":14},"D","0.6","2020版教材P306 \u002F 2019版教材P305 《水利建筑工程预算定额》中的土方定额。土方工程定额推土机的推土距离和铲运机的铲运距离是指取土中心至卸土中心的平均距离。推土机推土定额是按自然方拟定的，如推松土时，定额乘0.80调整系数。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]