[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151169":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1151169,803,1,"单选题","根据《水利建筑工程预算定额》，混凝土拌制定额均以（ ）计算。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","混凝土中间量",false,{"key":16,"text":17,"correct":14},"B","混凝土最终量",{"key":19,"text":20,"correct":21},"C","混凝土半成品量",true,{"key":23,"text":24,"correct":14},"D","混凝土成品量","2020版教材P307 \u002F 2019版教材P306 《水利建筑工程预算定额》关于混凝土拌制的规定。混凝土拌制定额均以半成品方为单位计算，不含施工损耗和运输损耗所消耗的人工、材料、机械的数量和费用。混凝土拌制及浇筑定额中，不包括加冰、骨料预冷、通水等温控所需的费用。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]