[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151168":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1151168,803,1,"单选题","水电工程设计概算项目划分为枢纽工程、建设征地和移民安置、（ ）三部分。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","独立费用",true,{"key":16,"text":17,"correct":18},"B","基本预备费",false,{"key":20,"text":21,"correct":18},"C","建设期贷款利息",{"key":23,"text":24,"correct":18},"D","项目建设管理费","2020版教材P308 \u002F 2019版教材P307 水力发电工程概（估）算编制方法，这里概算中的静态投资。项目划分水电工程设计概算项目划分为枢纽工程、建设征地移民安置补偿、独立费用三部分",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]