[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151162":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1151162,803,1,"单选题","下列不属于其他直接费的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","企业管理费",true,{"key":16,"text":17,"correct":18},"B","特殊地区施工增加费",false,{"key":20,"text":21,"correct":18},"C","夜间施工增加费",{"key":23,"text":24,"correct":18},"D","冬雨期施工增加费","2020版教材P310 \u002F 2019版教材P309 水利工程设计概估算编制规定中的费用构成。本题A选项为间接费，BCD均为其他直接费. 其他直接费包括冬雨期施工增加费，夜间施工增加费，特殊地区施工增加费，临时设施费，安全生产措施费和其他。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]