[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151159":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1151159,803,1,"单选题","分类分项工程量清单项目编码中500101002001的第五、六位为（ ）顺序码。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","水利工程",false,{"key":16,"text":17,"correct":14},"B","专业工程",{"key":19,"text":20,"correct":14},"C","分项工程",{"key":22,"text":23,"correct":24},"D","分类工程",true,"2020版教材P314 \u002F 2019版教材P313 分类分项工程量清单项目编码各部分锁代表的含义。分类分项工程量清单分为水利建筑工程工程量清单和水利安装工程工程量清单。分类分项工程量清单项目编码采用十二位阿拉伯数字表示（由左至右计位）。一至九位为统一编码，其中，一、二位为水利工程顺序码，三、四位为专业工程顺序码，五、六位为分类工程顺序码，七、八、九位为分项工程顺序码，十至十二位为清单项目名称顺序码。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]