[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151158":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1151158,803,1,"单选题","根据《水利工程工程量清单计价规范》GB50501-2007，工程量清单有分类分项工程量清单、（ ）、其他项目清单和零星工作项目清单组成。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","环境保护措施清单",false,{"key":16,"text":17,"correct":14},"B","安全防护措施清单",{"key":19,"text":20,"correct":21},"C","措施项目清单",true,{"key":23,"text":24,"correct":14},"D","夜间施工措施清单","2020版教材P314 \u002F 2019版教材P313 工程量清单的组成。招标文件中的工程量清单是投标报价的重要依据。根据《水利工程工程量清单计价规范》GB 50501—2007，工程量清单由分类分项工程量清单、措施项目清单、其他项目清单和零星工作项目清单组成。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]