[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151156":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1151156,803,1,"单选题","为完成工程项目施工，发生于该工程施工过程中招标人要求计列的费用项目为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","措施项目",false,{"key":16,"text":17,"correct":14},"B","零星工作项目",{"key":19,"text":20,"correct":14},"C","分类分项工程项目",{"key":22,"text":23,"correct":24},"D","其他项目",true,"2020版教材P314 \u002F 2019版教材P313 工程量清单计价规范其他项目的基本概念。其他项目指为完成工程项目施工，发生于该工程施工过程中招标人要求计列的费用项目。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]