[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151155":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1151155,803,1,"单选题","其他项目清单中的暂列金额一般可为分类分项工程项目和措施项目合价的（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","2%",false,{"key":16,"text":17,"correct":14},"B","3%",{"key":19,"text":20,"correct":21},"C","5%",true,{"key":23,"text":24,"correct":14},"D","10%","2020版教材P314 \u002F 2019版教材P313 工程量清单计价规范中的其他项目清单。其他项目指为完成工程项目施工，发生于该工程施工过程中招标人要求计列的费用项目。其中，暂列金额指招标人为可能发生的合同变更而预留的金额，一般可为分类分项工程项目和措施项目合价的5%。暂估价指在工程招标阶段已经确定的、但又无法准确确定价格的材料、工程设备或工程项目。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]