[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151153":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1151153,803,1,"单选题","下列说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","除合同另有约定外，现场工艺试验所需费用，包含在现场工艺实验项目总价中，由发包人按《工程量清单》相应项目的总价支付",false,{"key":16,"text":17,"correct":18},"B","承包人承担的超大、超重件的运输费用，由发包人按《工程量清单》相应项目的总价支付",true,{"key":20,"text":21,"correct":14},"C","除合同另有约定外，承包人根据合同要求完成施工用电设施的建设、移设和拆除工作所需的费用，由发包人按《工程量清单》相应项目的工程单价或总价支付",{"key":23,"text":24,"correct":14},"D","除合同另有约定外，承包人根据合同要求完成仓库或存料场的建设、维护管理和拆除工作所需的费用，由发包人按《工程量清单》相应项目的工程单价或总价支付","2020版教材P318 \u002F 2019版教材P317 承包人承担的超大、超重件的运输费用的由谁承担的问题。承包人承担的超大、超重件的运输费用，均由承包人自行负责，发包人不另行支付。超大、超重件的尺寸或重量超出合同约定的限度时，增加的费用由发包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]