[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151136":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1151136,803,1,"单选题","根据有关规定，机组启动验收，由（ ）进行。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目法人会同电网经营管理单位共同组织机组启动验收委员会",true,{"key":16,"text":17,"correct":18},"B","国家有关部门委托国家电力公司或其他单位会同有关省级政府主管部门共同组织工程蓄水验收委员会",false,{"key":20,"text":21,"correct":18},"C","项目法人会同有关省级政府主管部门共同组织工程截流验收委员会",{"key":23,"text":24,"correct":18},"D","项目法人自行组织","2020版教材P292 \u002F 2019版教材P291 水轮发电机组启动验收由项目法人会同电网经营管理单位共同组织验收委员会进行，并邀请省级发展改革委、能源主管部门，相关部门、项目法人所属计划单列企业集团（或中央管理企业）、有关单位和专家参加。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]