[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151135":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1151135,803,1,"单选题","水电工程验收过程中的争议，由（ ）协调、裁决。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","验收委员会主任委员",true,{"key":16,"text":17,"correct":18},"B","上级水行政主管部门",false,{"key":20,"text":21,"correct":18},"C","外聘专家",{"key":23,"text":24,"correct":18},"D","验收主持单位","2020版教材P292 \u002F 2019版教材P291 验收过程中如发生争议，由验收委员会主任委员协调、裁决，并将验收委员会成员提出的涉及重大问题的保留意见列入备忘录，作为验收鉴定书的附件。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]