[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151134":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1151134,803,1,"单选题","水电工程验收委员会主任委员裁决意见有半数以上委员反对或难以裁决的重大问题，应由（ ）报请验收主持单位决定。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","验收委员会",true,{"key":16,"text":17,"correct":18},"B","项目法人",false,{"key":20,"text":21,"correct":18},"C","验收主持单位",{"key":23,"text":24,"correct":18},"D","地方政府","2020版教材P292 \u002F 2019版教材P291 主任委员裁决意见有半数以上委员反对或难以裁决的重大问题，应由验收委员会报请验收主持单位决定，验收主持单位的裁决文件应作为验收鉴定书的附件，重大事项应及时上报省级人民政府能源主管部门。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]