[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151129":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1151129,803,1,"单选题","（ ）应及时将工程竣工验收总结报告、验收鉴定书及相关资料报送省级人民政府能源主管部门。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","竣工验收主持单位",true,{"key":16,"text":17,"correct":18},"B","竣工验收委员会",false,{"key":20,"text":21,"correct":18},"C","竣工验收委员会主任委员",{"key":23,"text":24,"correct":18},"D","项目法人","2020版教材P294 \u002F 2019版教材P293 验收委员会完成竣工验收工作后，应出具竣工验收鉴定书；验收主持单位应及时将工程竣工验收总结报告、验收鉴定书及相关资料报送省级人民政府能源主管部门。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]