[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151123":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1151123,803,1,"单选题","验收结论必须经（ ）似上验收委员会成员同意。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1\u002F3",false,{"key":16,"text":17,"correct":18},"B","2\u002F3",true,{"key":20,"text":21,"correct":14},"C","3\u002F5",{"key":23,"text":24,"correct":14},"D","1\u002F2","2020版教材P267 \u002F 2019版教材P270 工程验收结论应经2\u002F3以上验收委员会（工作组）成员同意。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]