[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151122":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1151122,803,1,"单选题","若1\u002F2以上的委员（组员）对验收过程中发现的问题有不同裁决意见时，法人验收应报请（ ）决定。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","验收监督管理机关",true,{"key":16,"text":17,"correct":18},"B","竣工验收主持单位",false,{"key":20,"text":21,"correct":18},"C","质量监督部门",{"key":23,"text":24,"correct":18},"D","县级以上人民政府","2020版教材P267 \u002F 2019版教材P270 若1\u002F2以上的委员（组员）不同意裁决意见时，法人验收应报请验收监督管理机关决定，政府验收应报请竣工验收主持单位决定。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]