[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151120":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1151120,803,1,"单选题","项目法人应自工程开工之日起（ ）个工作日内，制定法人验收工作计划，报法人验收监督管理机关备案。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","90",false,{"key":16,"text":17,"correct":18},"B","60",true,{"key":20,"text":21,"correct":14},"C","30",{"key":23,"text":24,"correct":14},"D","7","2020版教材P268 \u002F 2019版教材P271 项目法人应自工程开工之日起60个工作日内，制定法人验收工作计划，报法人验收监督管理机关和竣工验收主持单位备案；当工程建设计划进行调整时，法人验收工作计划也应相应地进行调整并重新备案。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]