[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151113":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1151113,803,1,"单选题","单位工程完工验收应具备的条件是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","单位工程已按批准设计文件规定的内容全部完成",false,{"key":16,"text":17,"correct":14},"B","已移交运行管理单位",{"key":19,"text":20,"correct":21},"C","单位工程所有分部工程已经完建并验收合格",true,{"key":23,"text":24,"correct":14},"D","少量尾工已妥善安排","2020版教材P271 \u002F 2019版教材P273 单位工程验收应具备以下条件：1、所有分部工程已完建并验收合格；2、分部工程验收遗留问题已处理完毕并通过验收，未处理的遗留问题不影响单位工程质量评定并有处理意见；3、合同约定的其他条件。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]