[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151110":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1151110,803,1,"单选题","阶段验收应具备的条件是工程（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","30%以上的分部工程已经完建且质量合格",false,{"key":16,"text":17,"correct":14},"B","所有分部工程已经完建且质量合格",{"key":19,"text":20,"correct":14},"C","30%以上的单位工程已经完建且质量合格",{"key":22,"text":23,"correct":24},"D","对分部工程完成量没有具体要求",true,"2020版教材P272 \u002F 2019版教材P275 根据工程建设需要，当工程建设达到一定关键阶段时（如截流、水库蓄水、机组启动、输水工程通水等），应进行阶段验收。工程阶段验收时，对于工程的单元和分部工程完成情况并没有具体条件要求，主要是根据工程建设的实际需要来确定是否进行阶段验收。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]