[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151107":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1151107,803,1,"单选题","水电站的第一台（次）机组启动验收由（ ）主持。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","竣工验收主持单位或其委托单位",true,{"key":16,"text":17,"correct":18},"B","验收委员会可委托项目法人",false,{"key":20,"text":21,"correct":18},"C","项目法人",{"key":23,"text":24,"correct":18},"D","主管部门委托项目法人","2020版教材P275 \u002F 2019版教材P278 首（末）台机组启动验收应由验收主持单位或其委托单位组织的机组启动验收委员会负责。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]