[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151106":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1151106,803,1,"单选题","水电站机组启动验收的各台机组运行时间为投入系统带额定出力连续运行（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","24h",false,{"key":16,"text":17,"correct":14},"B","36h",{"key":19,"text":20,"correct":14},"C","48h",{"key":22,"text":23,"correct":24},"D","72h",true,"2020版教材P275 \u002F 2019版教材P278 水电站机组带额定负荷运行时间为72h。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]