[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151105":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1151105,803,1,"单选题","根据《水利水电建设工程验收规程》SL223-2008，竣工验收应在工程建设项目全部完成并满足一定运行条件后（ ）内进行。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3个月",false,{"key":16,"text":17,"correct":14},"B","6个月",{"key":19,"text":20,"correct":21},"C","1年",true,{"key":23,"text":24,"correct":14},"D","2年","2020版教材P277 \u002F 2019版教材P280 竣工验收应在工程建设项目全部完成并满足一定运行条件后1年内进行。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]