[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151096":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1151096,803,1,"单选题","下列关于水利工程档案验收的说法，不正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","档案验收不合格，不得进行或通过工程的竣工验收",false,{"key":16,"text":17,"correct":14},"B","档案验收可分为初步验收和正式验收",{"key":19,"text":20,"correct":21},"C","档案正式验收由项目法人负责",true,{"key":23,"text":24,"correct":14},"D","档案验收抽查档案总数应在200卷以上","2020版教材P290 \u002F 2019版教材P289 凡档案内容与质量达不到要求的水利工程，不得通过档案验收；未通过档案验收或档案验收不合格的，不得进行或通过工程的竣工验收；档案专项验收可分为初步验收和正式验收，初步验收可由工程竣工验收主持单位委托相关单位组织进行；正式验收应由工程竣工验收主持单位的档案业务主管部门负责；根据水利工程建设规模，抽查各单位档案整理情况，抽查比例一般不得少于项目法人应保存档案数量的8%，其中竣工图不得少于一套竣工图总张数的10%，抽查档案总量应在200卷以上。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]